Kalingra Road : Tottenham

Civil Infrastructure

Project:Kalingra Road
Location:Tottenham, Victoria
Client
Start Date: June 2016
Completion Date:2016
Contract Value: $3m

Project Description

Civil Infrastructure for Grand Prix

Laverton Main Drain

Residential Subdivision

Project:Laverton Main Drain
Location:Laverton, Victoria
Client: Stocklands Developments Pty Ltd
Start Date: June 2011
Completion Date:2011
Contract Value: $5m (approx.)

Project Description

Excavation of Creek Channels involving approximately 110,000 m3 of earthworks. Construction of approximately 800 meters of 1800mm diameter drainage outfall pipeline. Construction of culvert structures. Construction of Rock beaching and Pilot channels

Laverton Main Drain

Residential Subdivision

Project:Laverton Main Drain
Location:Laverton, Victoria
Client: Stocklands Developments Pty Ltd
Start Date: June 2011
Completion Date:2011
Contract Value: $5m (approx.)

Project Description

Excavation of Creek Channels involving approximately 110,000 m3 of earthworks. Construction of approximately 800 meters of 1800mm diameter drainage outfall pipeline. Construction of culvert structures. Construction of Rock beaching and Pilot channels

1/18

Ingles Street : Port Melbourne

Residential Subdivision

Project:Ingles Street
Location:Port Melbourne, Victoria
Client: 
Start Date: 2014
Completion Date: 2014
Contract Value: $11.2 million

Project Description

Residential Sub Division

Glenferrie Road : Hawthorn

Water Drain

Project: Glenferrie Road Water Drain
Location: Hawthorn, Victoria
Client: Melbounre Water
Start Date: June 2017
Completion Date:2017
Contract Value: $2.3 million

Project Description

Melbourne Water Drain

Rees Road : Melton

Gas Main Trenching

Project: Rees Road Gas Main
Location: Melton, Victoria
Client
Start Date: June 2014
Completion Date:2014
Contract Value: $2.4 million

Project Description

Trenching for 150mm diameter Gas Main

Orbis Business Park : Deer Park

Commercial Sub Division

Project: Orbis Stage 1-7 : Ravenhall
Location: Deer Park, Victoria
Client
Start Date: June 2011
Completion Date:2014
Contract Value: $13 million

Project Description

Commercial Sub Division

Moorooduc Hwy : Mt.Eliza

VicRoads Roundabout

Project: VicRoad Roundabout
Location: Mt.Eliza, Victoria
Client: VicRoads
Start Date: June 2011
Completion Date:2011
Contract Value: $2.6 million

Project Description

Roundabout for VicRoads

Pentridge Village

Residential Subdivision

Project: Pentridge Village
Location: Coburg, Victoria
Client
Start Date: June 2001
Completion Date:On Going
Contract Value: $8.5+million (approx.)

Project Description

Demolition, Earthworks, Roads, Outfall Drainage, Concrete, Sewer, Water, Landscaping

Edgars Road Main Drain

Drainage System

Project: Edgars Road Main Drain
Location: Epping, Victoria
Client
Start Date: June 2011
Completion Date:2011
Contract Value: $2.8 million (approx.)

Project Description

Construction of approximately 500 lineal meters of Twin 2700 and twin 2100 mm diameter drainage outfall pipes
Construction of the associated sediment pond and floodway earthworks
Construction of major pit structures

Mace Way : Melbourne Airport

Road Duplication

Project: Mace Way 
Location: Melbourne Airport, Victoria
Client: Melbourne Airport
Start Date: 1/09/2015
Completion Date:9/11/2016
Contract Value: $7.7 million

Project Description

Mace Way Melbourne Airport road duplication